Bianca

Industry

dry cleaning · production and 30+ service points

Duration

52 wks

Team

not published

Disciplines

Development · Infrastructure · Design

Task

First reinforce the team to make the season, then pivot the architecture and build the platform: production, the point network and logistics with traffic and load forecasting. About a year — through to handover.

Result

Production, service points and logistics run as one loop. Routes and load are planned by forecast, not after the fact. The platform handed over to the in-house support team.

How it went

How it went52 wks

052 wks

  1. stage 1 · 4 wks

    Team boost for the season

    Development

    Task

    The season was close and the in-house team couldn’t make it. We reinforced it with our engineers and shipped what had to be out for the season.

    Result

    Made the season — the team went in reinforced, not in debt.

  2. stage 2 · 4 wks

    Architecture pivot

    DevelopmentDesign

    Task

    The existing architecture couldn’t hold production, the point network and logistics in one model. We redesigned the platform: one data model, an integration plan, a team to build it.

    Result

    Target architecture and integration plan approved, the team assembled around the platform.

  3. stage 3 · 16 wks

    The production-automation platform

    DevelopmentDesign

    Task

    A digital loop for the production process: stages, statuses, accounting, operator workstations.

    Result

    The production process runs through the platform from intake to release.

  4. stage 4 · 12 wks

    Integration with the point network

    DevelopmentInfrastructure

    Task

    Connect the customer loop of the distributed point network to production: an order from a point goes into production and comes back with statuses.

    Result

    Points and production run as one loop; the order status is visible at every step.

  5. stage 5 · 10 wks

    Logistics optimisation

    Development

    Task

    Routes between points and production with traffic taken into account, load forecasting for production and points, shift and run planning.

    Result

    Routes and load are planned by forecast, not after the fact.

  6. stage 6 · 6 wks

    Handover to support

    DevelopmentInfrastructure

    Task

    Documentation, runbooks, on-call shifts together with the in-house team, platform handover.

    Result

    The platform is run by the client’s in-house team.